Jam Black Brook Culvert Replacement, ME_FY12 Project
The goals of the project were: (1) To remove an obstruction to upstream
fish passage for brook trout, Atlantic salmon and other resident and migratory fish. (2) To
restore access to 9.8 miles of stream habitat upstream of the obstruction. (3) To restore natural
sediment and woody debris transport through the crossing site. (4) To improve flood capacity at
the Magog Road crossing, reducing the risk of debris jams or overtopping the road. (5) To
provide a demonstration site in mid‐coast Maine for an appropriate stream crossing developed
in cooperation with the municipality.
Jam Black Brook Interim Report_2012.pdf — PDF document, 7281 kB (7456539 bytes)